featured

FRCSW returns first E-2D Hawkeye to complete PMI-2

2 min read
FRCSW returns first E-2D Hawkeye to complete PMI-2

In this photo taken prior to COVID-19, artisans and support staff of the FRCSW E-2 program are pictured at the testline Aug. 21, 2018, as they welcome the command’s first E-2D inducted for PMI-2. The aircraft is one of two E-2Ds assigned to VAW-120 currently undergoing the 220-day PMI-2 maintenance cycle.

dcmilitary.com offers audio versions of articles using Instaread. Some words may be mispronounced.

Fleet Readiness Center Southwest (FRCSW) set yet another milestone Jan. 23, 2020 with the delivery of its first E-2D Hawkeye to complete periodic maintenance interval two (PMI-2).

FRCSW returned the aircraft to Carrier Airborne Early Warning Squadron 120 (VAW-120), headquartered at Naval Station Norfolk. The Hawkeye was inducted in August 2018.

Developed to replace the Navy’s existing E-2C airborne early warning system aircraft, the E-2D is the fourth variant and manufactured by Northrop Grumman. The aircraft completed its maiden flight in 2007, and three years later, the first E-2D was delivered to the Navy.


“Compared to the E-2C, the E-2D is a completely different animal,” said E-2 deputy program manager Chris Crawford. “Everything is newer: Newer technologies, avionics, newer test equipment and procedures.”

Technologically superior to its predecessors, the E-2D is equipped with a radar featuring electronic and mechanical scanning capability, an integrated glass tactical cockpit, and advanced tactical workstations and mission computer.

FRCSW performs two levels of scheduled maintenance on the airframe: a light periodic maintenance interval one (PMI-1) which is done at FRCSW Site Pt. Mugu and FRC Mid-Atlantic, and PMI-2, or a heavy maintenance, at Naval Air Station North Island.

FRCSW is the Navy’s sole provider of PMI-2 events on the E-2 airframe, and the 135-member staff assigned to the program will add the maintenance of the E-2D to the existing E-2C workload in Building 460.

PMI is based upon a 96-month cycle: PMI-1 completed every 48 months, followed by PMI-2 48 months later.

PMI-1 targets specific areas of the airframe (primarily the tail) where artisans inspect for corrosion, cracks, mechanical and electrical issues. The procedure requires about a 45-day turn-around time (TAT).

Though not a complete overhaul, PMI-2 is a major disassembly of the aircraft to the fuselage. Artisans remove the aircraft’s wings, engines, landing gear and tail. The aircraft’s corrosion preventive paint is removed and an in-depth metal assessment is performed targeting cracks, corrosion, exfoliation and other surface anomalies.

Guidance for PMI servicing of the E-2D is found in the airframes Interactive Electronic Technical Manuals (IETMS), or computerized maintenance manuals.

“All of the procedures aren’t covered in the IETMS, so we worked a lot of hand-in-hand with engineering getting some things done,” Crawford noted. “This was a prototype aircraft, the first we’ve done, so we’re working toward the 220-day (PMI-2) TAT.”

If customers authorize repairs that are outside of the scope of specification, the work is classified as an in-service repair (ISR). ISRs are funded separately and normally completed during the PMI event.

ISR work involving the replacement of some fiber optic lines in the VAW-120 aircraft was completed, while artisans also performed an age exploration analysis to the landing gear and rotodome.

FRCSW is currently performing PMI-2 on a second VAW-120 aircraft and recently inducted another E-2D from Air Test and Evaluation Squadron Twenty (VX-20) based at Naval Air Station Patuxent River, Maryland.

Guest

Dashboard Manage Account Log out